Laytime Calculator — Demurrage & Despatch

This laytime calculator works out how much laytime was allowed, how much was used once exceptions are deducted, and whether demurrage or despatch is due. It produces a simple laytime statement you can check against the charter party and the statement of facts.

Laytime allowed

Allowed laytime from
t
t / day

Per day of 24 consecutive hours, as agreed in the charter party.

Time counting

After NOR and any notice or turn time in the charter party.

Time not counting (from the statement of facts)

h
h

Rates

USD / day
USD / day

Half the demurrage rate, the usual term.

Laytime result

Demurrage due

$12,500.00

20 h 0 min on demurrage (0.8333 days)

Laytime allowed
5 d 0 h 0 min
Gross time
6 d 6 h 0 min
Less time not counting
− 10 h 0 min
Laytime used
5 d 20 h 0 min
Time on demurrage
20 h 0 min

Exceptions are deducted in full. Under "once on demurrage, always on demurrage", time lost after laytime has expired usually still counts, unless the charter party says otherwise.

Chartering support from SENA

Laytime statement

Simplified statement. Check every period against the signed statement of facts.

Laytime commencedMon 2 Nov 2026, 08:00
CompletedSun 8 Nov 2026, 14:00
Gross time6 d 6 h 0 min
Less: Rain — loading stopped− 6 h 0 min
Less: Shifting berth− 4 h 0 min
Laytime used5 d 20 h 0 min
Laytime allowed5 d 0 h 0 min
Demurrage: 20 h 0 min × $15,000/day$12,500.00

How to use the laytime calculator

  1. Set the laytime allowed. Either divide the cargo quantity by the agreed loading or discharging rate, or enter a fixed number of days from the charter party.
  2. Enter when laytime commenced and when operations were completed. Commencement normally follows the notice of readiness (NOR) plus any notice or turn time in the charter party.
  3. List the time that does not count, taken from the statement of facts: rain on a weather-working-day charter, Sundays and holidays under SHEX terms, shifting between berths, breakdowns of ship's gear and so on.
  4. Enter the demurrage rate. Despatch defaults to half demurrage, the usual term, but you can change it.

How laytime, demurrage and despatch are calculated

Laytime allowed = cargo (t) ÷ rate (t/day) [or a fixed number of days] Laytime used = completed − commenced − time not counting Demurrage = (used − allowed) in days × demurrage rate when used > allowed Despatch = (allowed − used) in days × despatch rate when used < allowed

Both demurrage and despatch are pro rata: a day is 24 consecutive hours, so 20 hours is 0.8333 of a day.

Key terms

  • Laytime: the time the charterer may use to load or discharge without paying extra, in addition to the freight.
  • Demurrage: liquidated damages the charterer pays for each day, or part of a day, that the ship is kept beyond the laytime.
  • Despatch: money the owner pays back for finishing early, usually at half the demurrage rate.
  • SHINC / SHEX: Sundays and holidays included, or excluded, from laytime. Under SHEX "unless used", Sunday time counts if the ship actually worked.
  • Weather working day (WWD): a working day that counts only if weather allows work; time lost to rain is excluded.
  • Reversible laytime: one allowance for loading and discharging together, so time saved at one end can be used at the other.

Worked example

A bulk carrier loads 50,000 t at 10,000 t per day, so 5 days (120 hours) of laytime are allowed. Laytime commenced at 08:00 on Monday 2 November 2026 and loading was completed at 14:00 on Sunday 8 November: 6 days 6 hours, or 150 hours, of gross time. The statement of facts shows 6 hours of rain and 4 hours shifting berth, so 140 hours were used.

  • Time on demurrage: 140 − 120 = 20 hours = 0.8333 days
  • Demurrage at USD 15,000 per day: 0.8333 × 15,000 = USD 12,500

Had the charter party been SHEX, the 14 hours on Sunday 8 November would also not count (unless the terms say "unless used" and the ship worked). Only 6 hours would then be on demurrage, about USD 3,750. The wording of the charter party decides every one of these points, which is why most laytime disputes are about the exceptions rather than the arithmetic.

Avoiding laytime disputes

  • Make sure the NOR is valid: the ship must be at the agreed place and actually ready in every respect.
  • Have the master and agent sign a detailed statement of facts with start and end times for every stoppage.
  • Record weather stoppages with times, and note whether cargo work actually stopped.
  • Remember that once the ship is on demurrage, most exceptions stop applying.

SENA's chartering and brokering team negotiates laytime terms and checks laytime statements every day. Planning a voyage? Estimate the time at sea with the voyage ETA calculator.

Frequently asked questions

What is the difference between laytime and demurrage?
Laytime is the time allowed in the charter party for loading or discharging, already paid for in the freight. Demurrage is the agreed daily amount the charterer pays when cargo operations run beyond that time.
When does laytime start?
After a valid notice of readiness and any notice or turn time in the charter party. For example, under GENCON 1994 laytime starts at 13:00 if NOR is given up to and including 12:00, and at 06:00 the next working day if NOR is given during office hours after 12:00.
What does "once on demurrage, always on demurrage" mean?
Once laytime has expired, the ship is on demurrage continuously, and the laytime exceptions (weekends, rain and so on) generally no longer interrupt it. Only clear wording in the charter party, or delays caused by the owner, stop demurrage running.
How is despatch calculated?
Despatch is usually paid at half the demurrage rate, pro rata. Charter parties say whether it is earned on "all time saved", which counts weekends and holidays, or only on "laytime saved" (working time saved). This calculator uses laytime saved, the more common basis.
What is reversible laytime?
With reversible laytime, loading and discharging share one allowance. Time used at the load port is added to time used at the discharge port and compared with the total. Calculate both ports and add them together.
Is demurrage the same as detention?
Not quite. In voyage charters, detention is damages for delay beyond any agreed demurrage period, or where no demurrage rate applies, and it must be proved. In container shipping, "demurrage" and "detention" mean charges for containers kept in or outside the terminal, which this calculator does not cover.

Arithmetic aid only. Laytime and demurrage depend on the exact wording of the charter party, the validity of the notice of readiness and the statement of facts, which this calculator cannot assess.